PE1682
PETITION NO. 1682 – VCP Groton LF, LLC d/b/a Verogy petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 4.975-megawatt AC solar photovoltaic electric generating facility and associated equipment located at the former Groton Landfill, 685 Flanders Road, Groton, Connecticut, and associated electrical interconnection.
PETITION (recd. 07/25/25)
Petition Narrative, 07/24/25
Appendices
Appendix A – Equipment Specifications, TCLP Report
Appendix B – Project Plans
Appendix C – Stormwater Calculations, Supporting Documents, Watershed Maps
Appendix D – Operation and Maintenance Plan
Appendix E – Decommissioning and Restoration Plan
Appendix F – Public Outreach
Appendix G – NDDB Approval Letter and USFWS IPaC Review
Appendix H – SHPO Review Letter
Appendix I – FAA Study Results
Appendix J – Wetlands Report
CGS §16-50k CORE FOREST AND PRIME FARMLAND DETERMINATIONS
Department of Energy and Environmental Protection C.G.S. §16-50k No Material Impact to Core Forest Determination Letter, 07/31/25
PROCEDURAL CORRESPONDENCE
Town Letter to Groton, 07/28/25
Council State Agency Comment Memorandum, 07/28/25
Council Notice of Incomplete, 07/28/25
Council Acknowledgement of Complete Petition, 08/06/25
SCHEDULE
Schedule, 07/25/25
Schedule, 08/06/25
SERVICE LIST
Service List, 07/25/25
PETITIONER - VCP Groton LF, LLC d/b/a Verogy
Response to Incomplete Notice, 08/4/25